Stage 1 plant-room consolidation across multiple historic plant zones, with new water-cooled chillers, cooling towers and BMS interlink pipework.
[ Challenge ]
Limited as-built documentation required full site survey to develop the concept brief. Dismantling and reassembly occurred in a confined plant room with height and load constraints.
[ Outcome ]
Optimised cooling efficiency and long-term operating cost reduction with minimal disruption to centre trading hours.
[ Scope ]
- 012 × 3,500 kW Water-Cooled Chillers and associated pumps
- 022 × 4,200 kW Cooling Towers and associated pumps
- 03New Mechanical Services Switchboards
- 04New Building Management System
- 05Stage-1 CHW, condenser and interlink pipework